Bricks arrived 2 weeks ago but there has been no sign of a bricky, the final framing issues have all been sorted out so we should be seeing some brick laying action.  Sounds like we are a lower priority to a couple of new display houses, next Monday is the day apparently.  Lets see if it happens.   To Ashford's credit they haven't just waited around,  the heating system ducts have been installed and the sparky has done a heap of the power, lighting and data cabling.  Damien tells me the internals and brickwork are all going to happen in parallel to catch up on some lost time.  May is getting close!



 Cut back the overhanging slab
Support the overhanging frame

Replaced base plate

Ducts

Theres going to be a lot of switches here


Power and data cabling

Temp front door