Thursday 26 January 2012

The roof is on...

I can't believe how fast they can get things done.  With the public holiday and an RDO on Friday they've only had three days this week in which the roof tiles have been laid and the windows and sliding doors are fitted as well as the door jams for the front and garage.   Some of the issues discovered last Friday have been fixed, the over hangs in the slab and entrance framing issue haven't been corrected yet.  Bit of a worry that the tiles are on but the framing requires some additional work.  Will be interesting to see how this will get sorted out.

Slab fix up
Extra nogen

                                             Cracked glass already

Extra stud added

Very glassy lounge\dinning room

Retreat doors

Entrance with door jam

Roof tiles, all done.